Completion estimate + 12 months. Invoice window: PED + 120 days. Retroactive extensions don't cure gaps.
Appropriation begins July 1; lapses June 30 six years later. CWA in fall of 5th year. Max extension: 2 yr.
Decrease ≥ $250K requires Exhibit 3-H. 23 CFR 630.106(a)(4).
Threshold raised from $750K effective FFY 2025. Subpart F applies.
Final Report of Expenditures due 6 months after construction acceptance. Releases 2%/$40K withhold.
$100M = Mini-Major (IFP/FPAU). $500M = Major (PMP + IFP + FPAU + CSRA, FHWA HQ concurrence).
Price cannot be a selection factor until the most qualified firm is identified. Aggregated scoring violates.
DLA Office Bulletins supersede the LAPM between annual publications. Cross-check before relying on any LAPM section.